www.benjawelding.com













Recieve our newsletter with
all news and updates



Unsubscribe




  • Best for pipping solutions
  • Butt Welding Machines
  • Logger Data Units
  • Installation Services

know more

ABOUT US

4

We would like to offer VB Welding Technology Co.,Ltd. (Hereinafter call "VB") to carry out the mechanical piping & installation (plumbing) work on your project. VB has a very successful record of projects going back over the last 10 years. With VB you can be assured of a quality work and materials supply at a competitive price.

VB offers its company profile to you for consideration. From this you can see that VB has over 20 years experience (old name "S.BEAM") by our founders Mr. Suthin Vittayabenjang in piping & plumbing installation also materials supply project contracted and has become popular for its high quality work combined with competitive pricing. You will see that VB is proud to provide quality workmanship and materials, and the scope of work, which can be carried out.

VB can carry out all phases of mechanical installation project from feasibility study, estimating, shop drawing work, construction, installation testing through to hand over. VB has the in depth knowledge and contacts in the Thai market to carry out Project smoothly. VB also has the highly skilled staff to achieve project development and completion within budget and on time.

This outstanding record of achievement is reflected in the references, which VB supplies to you. Due to this high reputation VB receives a lot offered work and further projects from established customers. This is your assurance that in entrusting you project to VB who has the in depth market knowledge to make it success; you have made the best choice.

For projects up to 100 million baht VB does the project by us and from our resources. For larger projects over 300 million baht VB may from a Joint venture with associated company can upon extensive technical experience in new areas of technology. To bring the best of the world technology for your project. This means that we are able to offer you a total service for all your project work. The souring of materials for your project will be made from the best of the world's suppliers. All you have to do is give us the contract and we will do the rest and take care of everything until we hand over your finished project. Naturally we will have regular project meetings keep you informed of progress. You can be confident that your project is a success.

VB and for large projects ours joint venture partner Abrantina can offer all the following service (see clause 2.3) all of which will be carried out as outlined above

Should your requirements not be in above list then we could call upon the worldwide expertise of our joint venture associated company to bring the necessary technology to bear upon your project.

4

In order to enable to fully consider the probability that VB is the best choice for your project we have pleasure earlier in submitting the company of VB in the following page.

There is no doubt that the company considers its most important asset to be its customers. The customers determine whether the company can meet their needs and expectations.

As well as investments in factory, know-how and training, customer relations set the foundation of success.

The company puts the customer in focus and draws on all its resources to ensure his satisfaction.

VB, Customers are always King, regardless of the size of his kingdom.

VB, Works in term of the company's policy, would mean the works, which meet the following qualifications.
? Meet the customer's needs and satisfactions
? Meet quality or meet at high level of any set standard - i.e.
Neat workmanship, function properly, reliable operation,
Durable or have long life
? Meet economical cost / benefit consideration
? Serviceable or convenient to maintenance, have possibility for
The future expansion or modification

6

The following features will convince you of the benefits that VB can bring to your project.

Project Estimating
First we carefully analyze your requirements and prepare and outline design. This is used to enable accurate estimation of the work involved and the materials required. Where necessary initial discussions may take place with suppliers to ensure sources of supply and to fix prices. This enables and accurate quotation to be prepared for consideration. In this way you can be sure that we have got the price right and the price is reasonable. It also means that as soon as the contract is made materials can be ordered so no time is lost.

Contract Award
Then we discuss the contract with you to make sure that you understand it and to clear any queries. As soon as all queries have been settled we proceed to sign a contract together. To confirm the contract and initial deposit of a proportion of the contract price is made.

Project Management
Next we set up a project planning and control system. This is to ensure that everything hoes according to plan. At regular intervals you are informed of progress. The project control is at a detailed level to ensure tight control overall aspects of the project.

Shop Drawings
The word of detailed shop drawing then commences. The shop drawing is carefully monitored and checked to ensure that it meets all your construction specification requirement in full. Highly experienced staffs are used to carry out the shop drawings and take further step to installation & erection in company with specification and original designed.

Procurement
The best sources of supplies of the fine quality at the most reasonable prices and the best delivery are located and detailed negotiations take place to ensure the most advantageous terms are obtained.
Orders are placed and progressed through to delivery. Of course material inspection is carried out to ensure that everything is correct.

Cost Control
A fine team of accountancy personnel carefully checks everything to ensure that the project remains within cost. Accounts are kept with great care and as appropriate stages of the project are completed these are invoiced to the client. This ensures that the cash flow during the project is kept within reasonable limits and is fair to all concerned.

Site Management
Highly experienced personnel carry out site surveys, supervise the preparation of the site, and control all works carried out. Of course the highest standards of safety and workmanship are maintained throughout. At the same time all materials are carefully checked and accounted for, and an inventory maintained any subcontractors used are carefully supervised to ensure that their work is of the highest standard. Site management maintains close liaison with project management to ensure timely completion of all project phases.

7

Quality Control
Quality controllers monitor all aspects of the project to ensure that the correct standards are adhered to throughout. Specifications are carefully checked against requirements and supplies to ensure that everything is in order. All works are meticulously inspected to ensure that they represent the best in workmanship. Quality control supervises testing to ensure a smooth hand over to the client.

Personnel
Only the most experienced and highly skilled personnel are uses on our client's projects. Personnel are carefully supervised and developed to attain their best potential. Our personnel are very dedicates to achieving the best for our clients. They want and know that you will be proud of their work.

VB aimed to work mainly in piping work and also plastic pipe (HDPE, LDPE, PB, PP) Field, and as the personnel were particularly experienced. However, the expansion and diversification had become necessary to serve extensive Customer's requirements, such as mechanical work (Piping & Plumping) and Capable to serve all kinds of industrial factory, and all kinds of Commercial building. Its services may include all materials and labors in turnkey basis or only labors for very large-scale projects. Scope of works for Installation of any project generally includes the installation of the following: -

General Work
- Portable water pipeline and water Supply System Transmission line Distribution system for industrial estate
Water work authority (PWA, MWA)
Golf course and factory and housing
- Sewage pipeline and water treatment plant
- Vacuum drainage, waste water drain to sea, sea water intake
- Drip irrigation and sprinkler for turf and landscape
- Chemicals industrial, food processing industry
- Plumbing work of sanitary system and septic - tank installation

 

Other than general works mentioned above, there may be some kinds of works, which require particular experiences of engineer or specialist; the company can also provide the efficient service for the following:

Specialist Work

- Mechanical work service
Water facilities pump installation
Piping of fire Fighting System Installation
Automatic fire detector system (Sprinkler with Head line manifold) and Fire Hydrant System,
Fire Pump Automation System
Plumbing Work of Sanitary System and septic System Tank Installation
- Plastic Pipe Work (HDPE, LDPE, PB, PP and PVDF)
Deck drainage (Storm water drainage)
Chemical laboratory drainage
Relining installation of HDPE pipe by inserting it into the existing pipe
Communication cable conduit
Electrical Cable Conduit

9

Year : 2005 -2006
Client / Owner : Provincial Waterworks Authority
Patumtani Province
Main Contractor : SINO - THAI Construction Co., Ltd (Public)
Project name : Rangsit - Lamlukka Patumtani Water Supply
Project Contract Amount : 6,815,900 Baht (Labors cost only)
Project Description : Local Distribution Network Pipeline
- LDN Route 4 HDPE pipe ? 400 mm PN 6.3
- LDN Route 5 HDPE pipe ? 500 mm PN 6.3
Installation main valve cost iron, Air vent
And Fire Hydrant
Duration of Project : November 2005 to July 2006
Project Location : Patumtani, Thailand
Project Result : Completed Hand-Over and on operation

Year : 2005 -2006
Client / Owner : Provincial Waterworks Authority
Chumphon Province
Main Contractor : Boonsaha Karnsang Ltd., Part
Project name : Chumphon portable water, Raw water Supply
Project Contract Amount : 10,215,000 Baht (Labors cost only)
Project Description : Portable water and Raw water Pipeline
- Portable water HDPE pipe ? 400 mm PN 6.3
- Raw water HDPE pipe ? 500 mm PN 6.3
Installation main valve cost iron, Air vent
And Fire Hydrant

Duration of Project : May 2005 to June 2006
Project Location : Chumphon, Thailand
Project Result : Completed Hand-Over and on operation

Year : 2001 -2003
Client / Owner : Provincial Waterworks Authority
Nakorn Pathom - Samut sakorn
Main Contractor : Joint Venture TWCK
Project name : Nakorn Pathom - Samut sakorn Water Supply
Project Contract Amount : 76,000,000 Baht
Project Description : Local Distribution Network Pipeline
- LDN Route 4 HDPE pipe ? 450 mm PN 8
- LDN Route 6 HDPE pipe ? 450 mm PN 8
- LDN Route 35 HDPE pipe ? 450 mm PN 8
- LDN Route 10 HDPE pipe ? 450 mm PN 8
- LDN Route 12 HDPE pipe ? 450 mm PN 8
- LDN Route 36 HDPE pipe ? 450 mm PN 8
And Steel pipe ? 400 mm
Installation HDPE pipe for Water Supply
Labors cost and Some Materials for installation
Duration of Project : June 2001 to March 2003
Project Location : Nakorn Pathom, Thailand
Project Result : Completed Hand-Over and on operation

ear : 1998 - 2000
Client / Owner : Expressway and rapid transit authority of
Thailand (E.T.A)
Bangkok Expressway Co., Ltd (B.EC.L)
Main Contractor : Joint Venture BBCD
Project name : BangNa - Bang Pli - Bang Pakong Expressway
Project ( Phase I,II,III,IV)
Project Contract Amount : 80,000,000 Baht
Project Description : HDPE Deck Drainage and PVC Duct Crossings
- Main Line Pier drain
- Widening drain
- Ramp drain
- Outer Ring Road drain
- CPEM Works
- Duct Crossings
Supply and Installation HDPE pipe
For Storm water drainage and Duct Crossings
For Electric cables.
Duration of Project : November 1998 to February 2000
Project Location : Bangkok, Thailand
Project Result : Completed Hand-Over and on operation

Year : 1998 - 2000
Client / Owner : Provincial Waterworks Authority
Main Contractor : Srikanokporn Karnyotha Co,Ltd
Project name : Provincial Waterworks Authority
Extension zone water supply
Project Contract Amount : 6,300,300 Baht ( Labor cost only )
Project Description : HDPE installation work and some materials
Supply Main valve, Air valve installation
Fire Hydrant & Hydro pressure test pipeline
Duration of Project : 24 months
Project Location : Phayao, Thailand
Project Result : Completed Hand-Over and on operation

Year : 1997 - 1998
Main Contractor : Srikanokporn Karnyotha Co., Ltd
Project name : Provincial Waterworks Authority
Extension Zone Water Supply Surin Province
Project Contract Amount : 3,800,000 Baht ( Labor cost only )
Project Description : HDPE and PVC Portable water pipeline
Main Values installation
Fire Hydrant and Air Valve installation
Concrete works
Duration of Project : October 1997 to March 1998
Project Location : Surin, Thailand
Project Result : Completed Hand-Over and on operation

Year : 1997
Main Contractor : Union Infratech Co.,Ltd
Project name : Irrigation Lampayong
Project Contract Amount : 2,800,000 Baht ( Labor cost only )
Project Description : Raw water pipe line
Duration of Project : February 1997 to August 1997
Project Location : Kalasin, Thailand
Project Result : Completed Hand-Over and on operation

Year : 1998 -1999
Main Contractor : NKK Engineering Co.,Ltd
Project name : TRI Energy Power Plant
Project Contract Amount : 4,600,000 Baht ( Labor cost only )
Project Description : Water pipe line
Sewer pipe line
Duration of Project : September 1998 - March 1999
Project Location : Ratchaburi, Thailand
Project Result : Completed Hand-Over and on operation

Year : 1996
Main Contractor : Intertech Thai Co.,Ltd.
Project name : Waste Water Treatment Plant
Bangkok - Dindaeng Phase I
Project Contract Amount : 4,300,000 Baht ( Labor cost only )
Project Description : Water pipe line (HDPE)
Duration of Project : March 1996 - November 1996
Project Location : Bangkok, Thailand
Project Result : Completed Hand-Over and on operation

8